LLP «SPETSSTROY»

The limited liability company "Company Spetsstroy" is registered as a legal entity on November 2, 1998 and operates in accordance with the current legislation of the Republic of Kazakhstan. The core businesses of the Company are construction and installation work, hydraulic engineering works of any complexity, as well as the construction of playgrounds and sports and recreation facilities.

The company has extensive experience in this area. Performs special complex construction works on bottom dredging of various water bodies of rivers, branches, canals, water areas.

So in the period from 2004-2011 bottom dredging works were performed at the sections of fish bypass channels at the mouth of the Ural River, at fish bypass channels at the mouth of the Kigach river, at the «Danayka» channel in Atyrau.

«Spetsstroy» Company has established itself as a reliable organization for the reconstruction and improvement of a number of water systems in the city of Almaty. For works there is the necessary specialized equipment, auxiliary equipment, qualified personnel. The company provides with good organization of work at the facility, maintains constant control over the quality of work in compliance with all construction rules and regulations of the Republic of Kazakhstan.

These indicators confirm a sufficient level of professionalism, including compliance with Safety Practice and the environmental law requirements of the Republic of Kazakhstan.

The period of 2011-2015 works at the facilities for the reconstruction of water protection zones and river channels in the city of Almaty performed.

The company has good production capacities, a number of special vehicles for work.

Special vehicles:

  • dump trucks
  • bulldozers
  • excavators
  • crane trucks
  • skidsteers
  • concrete pumps
  • mixer trucks
  • concrete mixing plants
  • concrete production plants

2015

Type of work: Reconstruction of individual sections of the riverbed and water protection zones of the Tiksai River.
City: Almaty (2nd construction phase).
District: Medeu.
Agreement: No. 18 as per contract dated 05.05.2015.
Amount: 139 776 000 tg.

 

2015

Type of work: Reconstruction of individual sections of the channel and water protection zones of the Sultankarasu River.
City: Almaty (3rd construction phase).
District: Medeu.
Agreement: No. 14 as per contract dated 05.05.2015.
Amount: 403 728 069 tg.

 

2015

Type of work: Reconstruction of individual sections of the riverbed and water protection zones of the Baskarasu River.
City: Almaty (3rd construction phase).
District: Medeu.
Agreement: No. 15 as per contract dated 05.05.2015.
Amount: 463 414 874 tg.

 

2015

Type of work: Capital repair of the sprinkler system and fences of the Central Park of the city of Almaty.
City: Almaty (3rd construction phase).
District: Medeu.
Agreement: No. 70 dated 04.23.2015
Amount: 331 095 630 tg.

 

2015 год

Type of work: Construction of playgrounds.
City: Almaty.
District: Medeu.
Client: Apartment Owners' Cooperative «Alisher» Dostyk street 89, Satpayev street 4.
Amount: 3 198 988 tg.

Name of worksUnit of measurementAmountCost th.tgThe total amount th.tg
Preparation of the base - cutting the expansion layer; - land grading; - earth compacting; - crushed stone bottoming with compacting Square meters 140 1,097 153,642
Playground foundation: - trauma-resistant surfacing with rubber base 14 mm; - sporting and gaming complexes foundation, 2 units. Square meters 140 18,778 2,628,867
Site Improvement: - benches with litter-boxes; - borders, curbs compacting Square meters 24 17,353 416,479
Total:       3,198,988
 

2015 год

Type of work: Construction of playgrounds.
City: Almaty.
District: Medeu.
Client: Apartment Owners' Cooperative "Tazalyk".Zhibek-Zholy street 59.
Amount: 7 338 117 tg.

Name of worksUnit of measurementAmountCost th.tgThe total amount th.tg
Preparation of the base: - cutting the expansion layer; - land grading; - earth compacting; - sand and gravel mix bottoming with compacting Square meters 375 2,162 810,73
Preparation of the football field base: - bottoming of 2 football goals; - installation of metal fencing L-80 m Square meters 375 13,74 5,152,810
- bitumen concrete depositing-10cm; - demolition work; - installation of basketball backboards; - installation of a curb of 57 cm Square meters 157,32 5,679 893,48
Site Improvement: - benches with litter-boxes pieces 4 120,275 481,097
Total:       7,338,117
 

2015 год

Type of work: Construction of playgrounds.
City: Almaty.
District: Medeu.
Client: Apartment Owners' Cooperative «Nur», Makataev st 46.
Amount: 6 767 760 tg.

Name of worksUnit of measurementAmountCost th.tgThe total amount th.tg
Preparation of the base: - cutting the expansion layer; - land grading; - earth compacting; - sand and gravel mix bottoming with compacting Square meters 360 2,162 778,303
Preparation of the football field base: - bottoming of 2 football goals; - installation of metal fencing L-78m Square meters 360 13,968 5,028,614
Basketball court 189 m2 (21 * 9) - bitumen concrete depositing H-5 cm; - demolition work, installation of basketball backboards; - installation of a curb of 57 cm Square meters 189 2,538 479,749
Site Improvement: - benches with litter-boxes pieces 4 120,275 481,097
Total:       6,767,760

 Our address:

Almaty, Festivalnaya street, corner of Dezhnev street
+7-727-239-92-03

RU EN KZ